Concrete work follows the same order on most jobs. The crew digs the footings, sets the steel, pours, saw cuts the joints, and then the walls go up. Each step brings its own hazards, and most of them can be planned before the first truck is booked.

This checklist walks one real foundation plan through that order and puts the OSHA rule next to each check. The plan's takeoff sets the size of the job, and the size of the safety plan with it: nine trucks means nine trucks backing up to the pump, and 59 dowels means 59 bar ends to guard.

Sample takeoff totals: 76.7 cubic yards of concrete and 3,461 pounds of rebar.

The sample job, sheet A100, drawn in code from the plan's own geometry. Each layer of the takeoff lifts out in turn, and the totals land on 76.7 CY of concrete and 3,461 lb of rebar.

What The Takeoff Tells Your Safety Plan

A takeoff counts what goes into the job. Read the same counts as the size of each hazard. These five come from the sample job, in build order: the City of Ocala Park Pavilion, one 11-sheet PDF from a public bid set. We are not affiliated with the City of Ocala, and the City does not endorse us.

01 Dig 26 Pads and trench legs
Ten pads and sixteen hairpin trench legs, plus the edge footing. Each is an open excavation until the pour.
02 Steel 59 Dowels
One #5 bar for each grouted block cell, standing up out of the footing until the block covers it.
03 Pour 9 Trucks
82.0 CY to order with a 7% waste allowance, delivered to one pump in one pour.
04 Saw cut 412 LF of joints
Every foot of saw cut makes silica dust that needs a control.
05 Block 14 Ft CMU walls
2,346 blocks at the restrooms. Walls over 8 feet need bracing and a limited access zone.

The Checklist, In Build Order

Five stages, each with what happened on the sample job and the checks that go with it. Mark each item Yes, No or N/A for your own job, and follow the linked standard for the full requirement.

Sheet A100, foundation plan of the sample jobAn 85 by 40 foot slab with a monolithic edge footing, ten pads, sixteen hairpin trench legs and block walls at the restrooms. The layers light up in build order: the footing excavations, the steel and the 59 dowels, the slab pour, the saw-cut control joints and the block walls.12345AB85'-0"40'-0"FOUNDATION PLAN, A100
  1. 01DigEdge footing, 10 pads, 16 trench legs
  2. 02SteelMats, hairpins, 59 dowels
  3. 03Pour82.0 CY, 9 trucks, pumped
  4. 04Saw cut412 LF of control joints
  5. 05Block14 ft CMU walls
  1. Dig The Footings

    On the sample job: the edge footing, ten pads, sixteen hairpin trench legs and the thickened band under the block walls. All shallow, all open until the pour.

    • Locate underground utilities before the excavation is opened, and contact the utility owners as the rule requires. 1926.651(b)
    • Have a competent person inspect the excavations each day before work starts, and again after rain or any other change that raises the hazard. 1926.651(k)(1)
    • Protect workers from cave-ins. A protective system is required unless the excavation is entirely in stable rock, or is less than 5 feet deep and a competent person finds no sign of a potential cave-in. 1926.652(a)(1)
    • Keep spoil, forms and rebar bundles at least 2 feet back from the edge, or hold them back with retaining devices. 1926.651(j)(2)
    • In trenches 4 feet deep or more, give workers a ladder, ramp or stairway within 25 feet of lateral travel. 1926.651(c)(2)

    More in our trench and excavation guide.

  2. Set The Steel

    On the sample job: pad mats, edge bars, hairpins on their plates and 59 dowels, all tied down. The dowels stand up out of the footing for the grouted block cells and stay exposed until the block goes over them.

    • Guard every protruding bar a worker could fall onto or into, so the impalement hazard is eliminated. Dowels, starter bars and vertical bars all count. 1926.701(b)
    • Order the caps or covers from the takeoff count, so none run short on the day. The sample needs cover for 59 dowels.
    • Keep form scrap with protruding nails and other debris cleared from work areas and passageways around the forms. 1926.25(a)
    • Book the footing and slab steel inspection a day or two ahead, so the last ties are not rushed before the trucks arrive.

    More in our construction housekeeping guide.

  3. Pour The Concrete

    On the sample job: one monolithic pour of 82.0 CY in nine trucks, pumped. Footings first, then the slab.

    • Plan the truck route and the spot where each truck backs up to the pump. A truck with an obstructed rear view needs a reverse alarm audible above the noise, or an observer who signals that it is safe to back. 1926.601(b)(4)
    • Set the pump where its outriggers bear on firm ground, as the pump maker requires, and keep the boom clear of overhead power lines. Pick the spot before pour day.
    • Give discharge pipes supports designed for 100 percent overload, and give compressed air hoses on the pumping system positive fail-safe joint connectors. 1926.702(e)
    • Use power trowels that shut off when the operator's hands leave the handles, and nonconductive or insulated bull float handles where they could touch energized lines. 1926.702(c), (h)
    • Wet concrete can burn skin and eyes. Provide the protective equipment the work calls for, including eye protection where splashes can reach the eyes. 1926.95(a), 1926.102(a)(1)
    • Order from your own quantities. Running short late in the pour puts one more truck in the backing lane while the crew rushes the finish.

    More in our struck-by hazards guide.

  4. Saw Cut The Joints

    On the sample job: 412 LF of control joints, cut 6 to 18 hours after finishing. Then the forms come off and the edge is backfilled.

    • Cutting concrete makes respirable crystalline silica dust. Choose the control before the saw arrives, and name the competent person who checks it. 1926.1153
    • Table 1 of the silica standard has a row for walk-behind saws: an integrated water delivery system that feeds water to the blade continuously, with the saw run and maintained as its maker says. 1926.1153(c)(1)
    • A different setup, such as a dry saw with a vacuum, falls outside that row. The exposure then has to be assessed and controlled under paragraph (d). 1926.1153(d)
    • Clean up with wet methods or a HEPA-filtered vacuum. Dry sweeping and compressed air are not allowed where they could add to exposure, except as the rule allows. 1926.1153(f)
    • The cutting window can fall at night. Light the work area and plan who is on site for the cut.

    More in our silica rule guide.

  5. Build The Block Walls

    On the sample job: 2,346 blocks in 14-foot walls at the restrooms. The block goes up to 9'-4" first, then to 14 feet with two bond-beam courses, with the cells grouted in lifts along the way.

    • Set a limited access zone on the side of the wall that will not be scaffolded: as wide as the wall is high plus 4 feet, along its full length. For the sample's 14-foot walls, that is 18 feet. 1926.706(a)
    • Only the workers building the wall enter the zone. It stays until the wall is supported against overturning and collapse, and for walls over 8 feet, until the bracing below is in place. 1926.706(a)
    • Brace masonry walls over 8 feet so they cannot overturn or collapse, unless the wall is already supported. Leave the bracing until the permanent supporting elements are in place. 1926.706(b)
    • On the scaffold, protect workers from falls above 10 feet, and give safe access when the platform is more than 2 feet above or below the access point. 1926.451(g)(1), (e)(1)
    • Masonry saws need a semicircular guard over the blade that retains blade fragments. Cutting block makes silica dust too, so the saw needs its silica control. 1926.702(i), 1926.1153

    More in our scaffolding guide.

Get The Quantities For Your Own Pour

Every number in this checklist came from a takeoff. Concrete Mix AI makes one from your own plans, free: the concrete, rebar and block quantities, each shown on your drawing with the math behind it.

  1. Send the full plan set A PDF exported from your CAD or design software with the drawings, general notes and specs, or DWG or DXF files with their references. Not a scan or a photo.
  2. Add your email No account and no login. The email is where the takeoff goes.
  3. Get the takeoff back A private link to your takeoff on your own drawing, with a 3D build-up and the build sequence of the job, and a quantities CSV for your pour plan and your orders.

Drawing conflicts come back as questions for your engineer. The sample job had two: the size of the F01 pads, and the slab strength, 3,000 psi on two drawing sheets against 5,000 psi in the specification table. You get quantities, not prices.

Estimate only. Verify before ordering.

Where Osha Ask Fits Around A Pour

Osha Ask reviews job site video and photos and checks what it sees against OSHA requirements. Around a pour, that covers visible conditions such as spoil piled at a trench edge, a trench without a way out or a worker without a hard hat. Each flag comes with the OSHA requirement it relates to.

Book a demo to see the checks on footage from your own site, or read about AI video safety monitoring and the construction site safety checklist.

Frequently Asked Questions

What should a concrete pour safety checklist cover?

The work in the order it happens: the footing excavations, the rebar, the pour with its trucks and pump, the saw cutting, and any block walls built on the new footing. Each stage has its own OSHA rules, linked in the checklist above. Add the checks your own job needs.

Do rebar dowels need caps?

Protruding reinforcing steel that a worker could fall onto or into must be guarded to eliminate the impalement hazard (29 CFR 1926.701(b)). Use covers or caps made to prevent impalement, or another guard that removes the hazard, and keep them on until the bars are covered by the work.

When does a block wall need bracing?

Masonry walls over 8 feet high must be braced so they cannot overturn or collapse, unless the wall is already supported, and the bracing stays until the permanent supporting elements are in place (29 CFR 1926.706(b)). While the wall goes up, a limited access zone as wide as the wall height plus 4 feet runs along the unscaffolded side (1926.706(a)).

Does saw cutting a new slab fall under the silica rule?

Cutting concrete releases respirable crystalline silica, so the construction silica standard, 29 CFR 1926.1153, applies unless exposure stays below 25 micrograms per cubic meter as an 8-hour average under any foreseeable conditions. Use the Table 1 row for walk-behind saws, or assess and control the exposure under paragraph (d).

How does a takeoff help the safety plan?

A takeoff counts what the job holds: the trucks, the dowels, the feet of saw cut and the wall heights. Those counts tell you how many caps to order, how long the truck line will be and how big the access zones are. The free takeoff from Concrete Mix AI gives you these quantities from your own plans, with the build sequence of the job. Estimate only. Verify before ordering.

What do I send for the free takeoff?

The full plan set as a PDF exported from your CAD or design software, not a scan, or DWG or DXF files with their references. Missing sheets mean missing quantities. If a scan is all you have, one scanned set is done as a courtesy; it takes longer.

Does the free takeoff need an account?

No. There is no account and no login. You send the plans and an email address, and the takeoff comes back to that address.

This page is general information, not legal advice. The linked OSHA standards set the requirements for your work.